Greetings neighbors,

We hope this message finds you safe and well. Below are the latest updates on our progress at "The Emery".

Power Connection Work in Streets

We are nearing inspection on the Halleck street work. PG&E has given us an inspection date of 11/4/2020.

EBMUD Water Connections

Our contractor will open up EBMUD "tie in" locations on Sherwin Ave and Horton St. this week in preparation for providing water on site. Once opened these "tie in" points will be covered until EBMUD can perform the work.

On Site This Week

Building B1 wood framing started last week and continues this week.

Building B2 will continue to form up and prep upper levels of the central parking garage, expect near term concrete placement activities 10/20 and 10/26.

Sanitary sewer installation along the western edge of the site is complete. Storm sewer work should be complete by early next week.

Building D building pad and footing installation restart by early November.

We have received a few questions about the exterior wall "mock ups" being constructed at the south end of the site along the Sherwin Avenue frontage. These mock ups help us demonstrate how we will sequence, detail, and build certain exterior conditions of our buildings. The location of these mock ups was determined by available space on site and they face inward so what is visible to the neighbors may look like the back of a movie set.

Have a safe week and we will be in touch with additional updates as the work progresses.