10012020 website aerial.JPG

10/6/20 Update

Greetings neighbors,

We hope this message finds you safe and well. Below are the latest updates on our progress at "The Emery".

Power Connection Work in Streets

Placement of the #7 box on Halleck Street is underway over the next 2 weeks. Please be advised of additional work in this area.

On Site This Week

Building B1 level 1 concrete placement tomorrow. Starting wood framing within next 2 weeks.

Building B2 will continue to form up and prep upper levels of the central parking garage for concrete placement projected for later this week and next week.

Sanitary and storm sewer installation along the western edge of the site continues until 10/22/20. After this work is complete Building D footings/foundation work will continue.

We have received a few questions about the exterior wall "mock ups" being constructed at the south end of the site along the Sherwin Avenue frontage. These mock ups help us demonstrate how we will sequence, detail, and build certain exterior conditions of our buildings. The location of these mock ups was determined by available space on site and they face inward so what is visible to the neighbors may look like the back of a movie set.

Have a safe week and we will be in touch with additional updates as the work progresses.