12/15/2020

Greetings neighbors,

We hope this message finds you safe and well. Below are the latest updates on our progress at "The Emery".

Power Connection Work in Streets

Halleck street power connection work was completed and PG&E "tie-in" date to energize the project is scheduled for 1/25/2021 - 1/29/2021. Please be on the lookout for a mailer from PG&E notifying you of any power disruption in your area. We will communicate any further details as we are made aware of them from PG&E.

Storm Water Installation on Sherwin Ave

We anticipate beginning installation of the storm drain trenching on Sherwin Ave the week of 12/14/2020. Please anticipate traffic control on Sherwin Avenue during this time period which may cause minor delays.

EBMUD Water Connections

EBMUD permanent water system tie in locations have been opened up at Sherwin & Hubbard and Horton and 46th street. EBMUD has connected the water mains to our site now so expect these locations to be patched soon.

On Site This Week

We received some rain this weekend which has affected our site access to buildings B1 & B2. We are working on getting all weather streets for Hubbard and 46th Street this week and next so that work can resume.

Building D foundation work continues.

We anticipate beginning construction on the foundation footings for Building C by the end of January/early February.

Please keep in mind that with the rainy season upon us there will be a greater need for street sweeping so we are compliant with local and state storm water ordinances.

Have a safe week and we will be in touch with additional updates as the work progresses.