Greetings neighbors,

We hope this message finds you safe and well and that your holidays are wonderful this year. Below are the latest updates on our progress at "The Emery".

Holiday Hours:

We will be working 12/21-12/23 this week; 12/28-12/31 next week.

Power Connection Work in Streets

Halleck street power connection work was completed and PG&E "tie-in" date to energize the project is scheduled for 1/25/2021 - 1/29/2021. Please be on the lookout for a mailer from PG&E notifying you of any power disruption in your area. We will communicate any further details as we are made aware of them from PG&E.

Storm Water Installation on Sherwin Ave

We anticipate beginning installation of the storm drain trenching on Sherwin Ave the week of 12/14/2020. Please anticipate traffic control on Sherwin Avenue during this time period which may cause minor delays.

EBMUD Water Connections

EBMUD permanent water system tie in locations have been opened up at Sherwin & Hubbard and Horton and 46th street. EBMUD has connected the water mains to our site now so expect these locations to be patched soon.

On Site This Week

Building B1 and B2 framing continues this week.

Building D foundation work continues.

We anticipate beginning construction on the foundation footings for Building C by the end of January/early February 2021.

Please keep in mind that with the rainy season upon us there will be a greater need for street sweeping so we are compliant with local and state storm water ordinances.

Have a safe week and we will be in touch with additional updates as the work progresses.