1/25/2021

RESCHEDULED

Storm Drain Installation on Horton Street

Now that sampling work is completed and storm drain work on Sherwin is wrapping up, the storm drain work on Horton Street will begin.

Due to inclement weather expected this week, we anticipate starting the storm drain work on Horton on 2/1/21. Completion is anticipated within 7-10 days weather permitting. There will be a vehicle traffic lane closure involved with this work so please avoid this area if at all possible during working hours. If you need to pass through this area please pay close attention to signs and flag persons providing traffic control.