Greetings neighbors,

Happy New Year 2022! We hope this message finds you safe and well. Below are the latest updates on our progress at "The Emery".

OFFSITE WORK:

Joint Trench Undergrounding Work on Horton Street:

The Joint Trench (power and telecom utility trenching) work on Horton Street between Sherwin Avenue and Park Avenue will continue on 1/10/22. Please be aware that extensive traffic controls will be in place during this work and it will take approximately 4-6 more weeks to complete. There will be saw cutting, heavy machinery excavation work, increased truck traffic for soil off haul, etc. occurring during working hours, generally 7am - 6pm each day.

45th & Hollis Intersection:

One of the improvements we are constructing as part of the development is a traffic signal at 45th and Hollis. The work is underway, and expect to be complete by week end. After this, work will be on hold while waiting for signal equipment to arrive.

ON SITE WORK:

Buildings continue to progress onsite at various stages of completion.

Our first two buildings are targeting occupancy by Q2/Q3 in 2022. There is still a long way to go to make those dates but we remain optimistic.