1/7/2021

Greetings neighbors,

Happy New Year 2021! We hope this message finds you safe and well. Below are the latest updates on our progress at "The Emery".

Power Connection Work in Streets

Halleck street power connection work was completed and PG&E "tie-in" date to energize the project is scheduled for 1/25/2021 - 1/29/2021. Please be on the lookout for a mailer from PG&E notifying you of any power disruption in your area. We will communicate any further details as we are made aware of them from PG&E.

Storm Drain & Recycled Water line Installation on Sherwin Ave

Storm drain and recycled water installation continues on Sherwin over the next couple of weeks. Please anticipate traffic control on Sherwin Avenue during this time period which may cause minor delays.

Storm Drain Installation on Horton Street

In preparation for installing new Storm drain on Horton Street between Sherwin Ave and 45th street we will need to pull several soil samples. That work will begin on 1/12/21 and no parking signs have been placed to alert our neighbors. Please be aware of this work and the significant traffic controls that will be in place from 1/12/21 through 1/14/21.

Once the storm and recycled water line work on Sherwin are completed (by the end of January 2021) the Horton Street storm drain installation will begin for about 1 week. During that time there will be significant traffic controls in place.

On Site This Week

Building B1 and B2 framing continues this week.

Building D foundation work continues.

We anticipate beginning construction on the foundation footings for Building C by the end of January/early February 2021.

Please keep in mind that with the rainy season upon us there will be a greater need for street sweeping so we are compliant with local and state stormwater ordinances.

Have a safe week and we will be in touch with additional updates as the work progresses.