03112021 Traceair Capture.JPG

3/16/2021

Greetings neighbors,

We hope this message finds you safe and well. Below are the latest updates on our progress at "The Emery".

OFFSITE WORK:

Power Connection Work - June/July

We anticipate a power interruption when we connect our permanent power to the site; estimated June/July 2021. We will continue to request clearer communication and more careful planning by PG&E for future planned outages that affect the neighborhood. Thanks for your patience.

Reclaimed Water Line Install - Sherwin Ave.

This work has been completed but there are a few punch list repair items that need to be addressed starting next week. Please be careful as there will be excavation work in a few areas on Sherwin Avenue. Traffic controls will be in place.

ON SITE WORK:

Building B1 roof completion, window installation, and continued work on mechanical, plumbing, electrical, etc. rough installations.

Building B2 wood framing on the 5th level. Mechanical trades are working inside the garage and the wood frame structures.

Building D placement of concrete podium slab, columns, and walls continues with wood framing starting in next couple weeks.

Building C (last one!) footings and foundations are now underway.

Concrete placement - there are roughly 4 or 5 large concrete placements left for this site over the next 4-5 weeks, which will be a nice milestone to have behind us.

Please keep in mind that with the rainy season upon us there will be a greater need for street sweeping so we are compliant with local and state stormwater management ordinances.

Have a safe week and we will be in touch with additional updates as the work progresses.