3/29/22 Update

Greetings neighbors,

We hope this message finds you safe and well. Below are the latest updates on our progress at "The Emery".

OFFSITE WORK:

Joint Trench Undergrounding Work on Horton Street:

The Joint Trench (power and telecom utility trenching) work on Horton Street between Sherwin Avenue and Park Avenue is still in progress. Underground trenching has been completed. Sidewalk improvements along the West side of Horton Street adjacent to the businesses are ongoing.

Please be aware that extensive traffic controls will be in place during this work and it will take approximately another 2 weeks to complete. There will be increased truck traffic occurring during working hours, generally 7am - 6pm each day.

45th & Hollis Intersection:

One of the improvements we are constructing as part of the development is a traffic signal at 45th and Hollis. We anticipate completion of this intersection by late April 2022.

Horton Street Paving

Significant paving operations on Sherwin Avenue have been delayed until 4/11/22. This is scheduled to last 10 days. The Horton Street paving work has been postponed until Steelwave (our office building neighbor) completes the bulk of their work to eliminate potential damage. There will be additional noise and odors from the paving machines. Traffic controls will be in place however please plan extra time to get through these areas.

ON SITE WORK:

Buildings continue to progress onsite at various stages of completion.

Our first two buildings are targeting occupancy by Q2 2022. There is still a long way to go to make those dates but we remain optimistic.