8/4/2020 Construction Update

Greetings neighbors,

We hope this message finds you well. Here are the latest updates on our progress at "The Emery".

Concrete Placement Work

We tentatively plan to place concrete on site at Building B2 on the 14th, 17th, and 21st of August. We may need noise waivers from the City for those days but we will confirm the timing later this week. Stay tuned...

Power Connection Work

As noted in our last update our contractor shifted their power connection efforts from Halleck & Park to Sherwin Avenue. The trenching will continue on the north side (Sherwin Williams side) of the street from the corner of Halleck and Sherwin all the way up past Hubbard then switching to the south side of Sherwin street near the Horton Street intersection. This work was described in our 6/29 update post as follows:

3. Sherwin Avenue (From Hubbard to Halleck): 16 Days

  • Trenching under north side of Sherwin Ave along project frontage
  • Trenching under existing sidewalk on Sherwin Ave
  • Traffic control signage and personnel as needed.

4. Sherwin Avenue (From Horton to Hubbard): 13 Days

  • Trenching under sidewalks along project frontage north side of Sherwin Ave.
  • Trenching across Sherwin Ave to new street lights
  • Trenching across Sherwin Ave then under sidewalk on South side of Sherwin to set #7 Box.
  • Traffic control signage and personnel as needed.

Thanks for your patience as we shift the sequencing of the power connection work for the next roughly 21 days.

On Site This Week

Building B2 will continue to form up and prep upper levels of the central parking garage for concrete placement over the next couple weeks.

Building B1 (closest to Sherwin & existing office building) will start vapor intrusion mitigation system installation this week in preparation for slab placement.

On site sanitary sewer and storm drain deep utility line installation begins next Monday 8/10 and over the next 45 days.

Have a safe week and we will be in touch with additional updates as the work progresses.