9/18/20 Construction Update

Greetings neighbors,

We hope this message finds you well. It has been awhile since we have posted but not much has changed from our previous work on the project, just more of the same. Below are the latest updates on our progress at "The Emery".

Power Connection Work in Streets

Sherwin Avenue power connection work is wrapped up for now and work is continuing on site where possible.

We will place a #7 box on Halleck Street very soon to facilitate our power connection to the site.

On Site This Week

Building B1 podium slab forming and preparation continues.

Building B2 will continue to form up and prep upper levels of the central parking garage for concrete placement projected for the

Storm sewer work is continuing on site this week and will probably wrap up in a couple of weeks.

***Another -- Temporary Haul Route Change***

Due to storm sewer installation work on site along the Hubbard Street extension near Sherwin Ave, trucks will not be able to exit the site at the Hubbard street exit as is typical. We anticipate trucks entering and leaving the site from the Halleck street entrance during the first 3 days next week 9/21, 9/22, and 9/23 while the Hubbard street sewer work is completed. We will still direct trucks to leave via Hubbard Street (approved haul route) once they exit at the Halleck entrance, but please be aware there may be trucks that exit down Halleck by mistake.

Have a safe week and we will be in touch with additional updates as the work progresses.