Greetings neighbors,

We hope this message finds you safe and well. Below are the latest updates on our progress at "The Emery".

PG&E POWER INTERRUPTION:

We expect our Phase II onsite power to be connected to buildings C & D the week of May 23rd 2022. PG&E crews will be onsite that week connecting our onsite transformers, etc. We expect portions of the neighborhood to experience an interruption of power during the day for this work. We do not have exact details on who will be affected yet. We will continue to follow up with PG&E for this information. It is our understanding PG&E will be sending notices to the affected neighbors.

OFFSITE WORK:

Joint Trench Undergrounding Work on Horton Street:

The Joint Trench (power and telecom utility trenching) work on Horton Street between Sherwin Avenue and Park Avenue is still in progress. Underground trenching has been completed. Sidewalk improvements along the West side of Horton Street adjacent to the businesses are ongoing in one section where existing live gas line vaults need to be raised. We are working with PG&E on how they want this work completed.

Please be aware that extensive traffic controls will be in place during this work and it will take approximately another 2 weeks to complete. There will be increased truck traffic occurring during working hours, generally 7am - 6pm each day.

45th & Hollis Intersection:

One of the improvements we are constructing as part of the development is a traffic signal at 45th and Hollis. We anticipate completion of this intersection by late May 2022.

Horton Street Paving

The Horton Street paving work has been postponed until Steelwave (our office building neighbor) completes the bulk of their work to eliminate potential damage. We will let you know when we are closer to that work occurring. There will be additional noise and odors from the paving machines. Traffic controls will be in place however please plan extra time to get through these areas.

ON SITE WORK:

Buildings continue to progress onsite at various stages of completion.

Our first two buildings are targeting occupancy by Q2 2022. We plan to open our leasing office on site last week of June. We have started pre-leasing as of this week.