Update for week of 2/17

Construction will start 2/18

The GC will be installing the Halleck construction entrance (Gate A) as approved in the CMP (Construction Management Plan).

The contractor will continue soil off haul activity this week so expect increased truck activity.

Street sweeper measure have been put in place as follows:

  • During heavy off-haul- sweeper will be running during construction hours.
  • On days where there light off-haul – sweeper will be running 12-4.